Basque Government creates table for New Euskadi Electrical Grid to accelerate investments

The plan foresees increasing power by 6,000 MW and will generate 18,000 jobs in the value chain between 2027 and 2030.

Generic image of high-voltage electrical towers and power lines over a green landscape.
AI

Generic image of high-voltage electrical towers and power lines over a green landscape.

The Basque Government, Provincial Councils, Iberdrola and Red Eléctrica have launched the Table for the New Euskadi Electrical Grid to speed up investments that will increase grid power by 50%.

Key points

  • Increase of 6,000 MW in Euskadi grid power
  • Creation of 18,000 jobs in the value chain
  • More than 20 actions in existing substations
  • Construction of 10 new substation parks
The Table will meet in January and July 2027 to evaluate and monitor the execution of investments. The objective is to coordinate a schedule of priority actions based on technical criteria. This planning foresees an increase of 6,000 MW in Euskadi's electrical power, addressing an additional demand of 2,300 MW in transmission and 3,000 MW of access capacity in distribution.
To achieve this increase, work will be carried out in almost all existing substations with more than 20 actions and 10 new substation parks will be built. Iberdrola will invest around 900 million euros between 2027 and 2030 in strengthening and digitising the distribution network. The company estimates that 18,000 jobs will be mobilised throughout the value chain during the execution of these works.
“

"We trust that the Regulatory Highway currently being processed in the Basque Parliament will help accelerate the execution of these investments over the next five years."

Mikel Jauregi · Councillor for Industry, Energy Transition and Sustainability
To accelerate investments, two levers will be activated: reducing approval times through the Urgent Simplification Law (Regulatory Highway), which will reduce permits from 24 to 6 months, and attracting specialised talent. The Basque Government will create a Working Group with Lanbide and Vocational Training to cover personnel needs in electromechanical assembly and digital solutions.
The actions will be distributed across the three territories. In Araba, a new substation will be built south of Vitoria-Gasteiz and the Ayala substation will be improved. In Bizkaia, the capacity of Gatika will be expanded for the Zamudio Technology Park and the Santurtzi substation will be modernised for port electrification. In Gipuzkoa, the new Azpeitia substation will guarantee supply, while the expansions of Ormaiztegi and Oiartzun will support the industrial recovery of Goierri and the development of Oarsoaldea.
Based on information from the official source: Irekia — Dpto. Industria, Transición Energética y Sostenibilidad (25/11/2026)