Port of Barcelona launches tender to create company managing ship-to-shore electricity

The new entity, with 30% public participation, will develop the OPS network to electrify docks by 2030.

Generic image of an electrical connector on a dock, with a blurred ship in the background.
AI

Generic image of an electrical connector on a dock, with a blurred ship in the background.

The Port of Barcelona has approved launching a public tender to award a concession for a company that will build and operate the ship-to-shore electricity network using OPS systems, a global investment of 1.7 billion euros.

Key points

  • Total investment of 1.7 billion euros (780 public and 920 private)
  • The concessionaire company will have 30% participation from the APB
  • Full deployment of the OPS network to be completed before 2030
  • The Port substation to be operational in the first quarter of 2027
The Board of Directors of the Port of Barcelona has given the green light to the launch of this public tender, aimed at awarding a concession for the design, construction, operation, and maintenance of the ship-to-shore electricity supply service. This infrastructure, known as Onshore Power Supply (OPS), will allow ships to turn off their engines while docked, reducing emissions in the port.
The management model foresees the creation of a single concessionaire company, in which the Barcelona Port Authority (APB) will maintain a 30% stake. This public-private partnership structure seeks to optimise investments, ensure coordinated planning for future expansions, and facilitate homogeneous service provision, generating economies of scale in operation and maintenance.
The new company will continue works already started at the Port, such as the Port substation, medium-voltage networks, and the initial deployment of OPS on the docks. The entity will be responsible for completing the electrical infrastructure, including transformation centres, ship connection systems, and cable management systems. This initiative is part of the Port of Barcelona Energy Transition Plan, which includes the Nexigen Plan for dock electrification.
Regarding timelines, the Port substation, connected to the Cerdà substation of Red Eléctrica Española with an 80 MW connection, will be operational in the first quarter of 2027. The first OPS systems for cruise terminals will be installed the same year, while the full deployment of the network in all container, ferry, and cruise terminals must be completed before 2030.
Based on information from the official source: Port de Barcelona - Sala de prensa (25/11/2026)