Tenerife Council allocates €518,000 to rehabilitate water supply in El Rosario
The grant will restore the connection between the Barranco Hondo well and the canals after ten years out of service.
By Airam Cabrera Suárez
••2 min read
AI
Generic image of industrial pipes and valves in a technical room.
The Tenerife Council has approved a direct grant of €518,137 to the El Rosario Town Council to rehabilitate the regulating reservoir and restore the water supply connection after more than ten years out of service.
Key points
Nominal grant of €518,137
Estimated execution period of 16 months
Co-financing by MEDI and FDCAN
The initiative, managed through the Department of Natural Environment, Sustainability, Security and Emergencies, aims to restore the connection between the Barranco Hondo well, the Araya Canal and the Río Portezuelo Canal. The hydraulic installations have been in a serious state of disrepair for over a decade.
The mayor of El Rosario, Escolástico Gil, stressed the importance of connecting the two canals with the Barranco Hondo reservoir to guarantee supply in the midlands and La Esperanza. The local mayor recalled that the severity of the forest fire in August 2023 highlighted the need for a unified system to prevent supply collapses.
“
"The severity of the Tenerife forest fire in August 2023 highlighted the importance of having a unified system to prevent the midlands and La Esperanza from losing supply if the canals collapse."
The action responds to measures in the Island Water Emergency Declaration approved in 2024, which called for interconnection between the two canals. Although the declaration has ended, reports from the Island Water Council justify the work to address structural deficiencies in the municipal network.
“
"With the approval of this aid... the Council responds to an urgent need in the municipality of El Rosario. We finance 100% of the rehabilitation of the regulating reservoir and the pumping... thereby guaranteeing the necessary resources in advance."
The works will include the renovation of the pumping room, affected by dampness, the dismantling of an unused aerial transformation centre, the complete replacement of mechanical equipment and load tests on conduits located in steep terrain. Funding comes from the Canary Islands Development Fund (FDCAN) and the Multiannual Strategic Framework for Actions for the Development of Tenerife (MEDI).